Pavement Resurfacing – B09 Hallowmoor
We are due to start pavement resurfacing in your area week commencing 9 May 2016, see overleaf for more information. Due to the high volume of traffic, businesses and shoppers in this area we have scheduled this work to take place during the night, under a road closure. Our working hours will be between 7.00pm and 5.00am. We apologise for any inconvenience this may cause and any noise you may experience.
Temporary road signs will be displayed five days before work starts, stating the dates of work and parking restrictions on your road.
Parking and access arrangements
There will be no on-street parking or vehicle access to properties on the roads we are working on, during working hours. Most roads will be open and on-street parking will be as normal at other times. Please let our on-site supervisor know if you need vehicle access to your property for urgent reasons. Pedestrian access and access for emergency vehicles will be available at all times.
Vehicles left on-street during restrictions may be towed away and you will need to pay a fee to have your vehicle released.
Please note that the schedule is heavily dependent on the weather and can be affected by unforeseen circumstances. Temporary road signs will be updated to reflect any changes.
We apologise for any inconvenience this may cause. For the latest updates please visit http://www.sheffield.gov.uk/hallowmoor or follow on Twitter @sccstreetsahead #SAB09

amey

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: