B42 Sharrow Vale – Road Resurfacing June 2016

1 Jun

Streets Ahead planned work schedule is set out below and gives information about the weeks when work will take place. The specific dates of work for each street will be displayed on the on-street signs five days in advance.

 

Please note that the schedule is heavily dependent on the weather and can be affected by unforeseen circumstances. It may be necessary to change the schedule at short notice. If this happens, the temporary signs displayed in the area will be updated.

 

Road Name Date of First Road Closure (Week Commencing) Working Hours
Sandbeck Place 13 June 2016 7am – 7pm
Osberton Place 13 June 2016 7am – 7pm
Cowlishaw Road 13 June 2016 9:30am – 2:30pm
Lescar Lane 13 June 2016 7am – 7pm
Kirkstall Road 13 June 2016 9:30am – 2:30pm
Bowood Rd 13 June 2016 7am – 7pm
Wayland Rd (Remainder of) 13 June 2016 7am – 7pm
Collegiate Crescent 13 June 2016 7am – 7pm
Broomgrove Rd 13 June 2016 7am – 7pm

 

They may also need to close the roads on additional days to make adjustments to ironwork such as manhole covers and road markings.

Further information

Please visit www.sheffield.gov.uk/sharrowvale for further information and updates about local works, you can also follow progress on Twitter @sccstreetsahead #SAB42.

If you would like to discuss any issues, please contact us on 0114 273 4567 or email streetsahead@sheffield.gov.uk. 

Thank you

We appreciate that any disruption can be frustrating and thank you for your understanding whilst these important works are completed.

 

Streets Ahead

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: